New Shear Commissioning

CIZALLA LEFORT 1

In June 2025, the commissioning phase of the Lefort Coloss 1000 shear was completed. With a total investment of €1.7 million and after a two-year wait, the aim is to process a larger volume of scrap metal more efficiently and with full respect for the environment. Equipped with the latest technology from the Belgian manufacturer Lefort, the shear can process 25-35 tons of scrap metal and handle many materials that were not previously processed at Hierros y Metales Sainz. We thank the teams at Lefort and Hirukei Maquinaria Bizkaia, S.L.U. for their commitment, dedication, and effort in bringing this project to fruition. We also extend our special thanks to the Provincial Council of Bizkaia (DFB), through the 2i program, for their collaboration and support in this public-private partnership.